<< Click to Display Table of Contents >>
SD-I Routings Defaults
Field Explanations
Multiply or Divide by Num Processes [M,D]
This sets the default for the prompt of the same name within the #Proc window found in each of the three routings entry programs. See RO-A Enter Routings for a detailed explanation of how the number of processes can be divided into or multiplied by the processes/hour.
Use Standard Time [Y,N]
Sets the Std Time? default in routings entry. If set to yes, the system will apply standard time to any units reported through WO-F Enter Labor rather than require actual time to be entered.
Make Seq equal Template Number [Y,N]
If you copy in operation templates, setting this default to Y causes the program to assign the routing sequence the same number as the template, wherever possible. Use this if you want sequences and operations to have the same numbering.
Default Seq increment
When copying in multiple operation templates into routings, the program automatically assigns sequence numbers. This field sets the default increment. For example, if you like your routing sequences numbered 10, 20, 30, etc., enter a 10. If you want your numbering 1, 2, 3, etc., enter a 1.
Display Long Time Prompt
Normally time is entered in hours, minutes, and seconds. If you prefer entering decimal time, or if the number of hours per part is ever to exceed 99 hours, or you need greater precision for high production operations than 1 second per part can provide, you can have an optional decimal field display in a pop-up window that will allow entry of up to 9,999 hours and seven decimal places. Answer Y to this prompt if you want the Long Time field displayed during routings entry.
Sync Template Settings to RO-A (Y/N/A)
If this is enabled then changes to time standards in templates will update master routings. If set to A, you will be asked if the master routings should be changed.