WO-K-G Recalculate Projected Hours
Purpose of Program
Use this program to recalculate the labor hours remaining by sequence based on the hours reported to date and percent complete.
General Program Operation
You can only run this program if you have set the "Use Projected or Estimate $ and Hours?" to P for Projected in SD-B Work Orders Defaults. You can limit the work orders to be recalculated by clearing Status Codes and Priority Codes in the first two fields. You can then enter a from/thru range of work order numbers.
You can further limit the work orders to be scheduled by entering from/thru ranges of work order numbers, Start Dates, Finish Dates, and work order Class Codes.
Once all filters have been entered, the program will recalculate the hours remaining by sequence based on the hours reported to date and the percent complete. Thus, if a sequence was originally estimated to take 10 hours and now there are 8 hours reported but it is only 50% complete, the estimated hours will be reset to 16 total, leaving a balance of 8 hours remaining to be scheduled. Sequences that are complete or have had no time or quantity or percent complete reported will not he changed. You can compare the original estimated hours to the current projection using WO-L-H Print Projected vs Estimated Hours